loganjmuir
Well-Known Member
"A new giraffe house structure was constructed between 1943 and 1950; most likely in the post war period. By 1943 a high wall had been constructed at the southern edge of the original Giraffe Enclosure (Figure 19) and by 1950 a new pyramidally roofed Giraffe House had been constructed south of that southern wall, although the wall remained in place, suggesting two giraffe ‘yards’ were in operation."
Judging by this sub-paragraph, the former zebra exhibit, now combined with the main yard, was originally intended to hold Giraffe as well. I would think in order to setup a breeding hub in the small site, but plans appeared to flail, and Giraffe never inhabited the lower yard.
"Although the s170 inventory noted Tahr Mountain as in good condition, an inspection in July 2016 undertaken for this project by the heritage specialists, the design team and structural engineers revealed that water ingress into the structure though the imitation rock cladding has resulted in significant corrosion and deterioration most particularly to the imitation rock cladding layer but also to the supporting concrete frame. In some areas light was visible through the cladding layer indicating areas of water ingress.
The report concluded that the extent of spalling damage observed to the structural framing of the mountain has not yet severely compromised the structural integrity. However, if the damage is left untreated and allowed to continue, it will eventually result in localised beam/column failures, which could compromise the stability of the structure and necessitate extensive remedial works or demolition. The report identifies action to repair the reinforced concrete frame. In relation to the ferro-concrete cladding the report states that it is generally in very poor condition, and localised failures could occur at any time where, dependent on their extent, could result in the injury/death of animals on the mountain. The report recommends that internal repair of the cladding be undertaken, using temporary propping of cladding panels between supporting columns to allow for drummy material and heavily corroded reinforcement to be cut back and removed, prior to installing new reinforcement and reinstating the original surface profile by spraying with shotcrete.
This makes it sound like Tahr were already on their way out prior to the reintroduction of Lions to the site. They had to be moved nevertheless however in order to accommodate the Pride, so it's not as alarming a move as it could have potentially been, had the structural engineers not caught wind of it.
Judging by this sub-paragraph, the former zebra exhibit, now combined with the main yard, was originally intended to hold Giraffe as well. I would think in order to setup a breeding hub in the small site, but plans appeared to flail, and Giraffe never inhabited the lower yard.
"Although the s170 inventory noted Tahr Mountain as in good condition, an inspection in July 2016 undertaken for this project by the heritage specialists, the design team and structural engineers revealed that water ingress into the structure though the imitation rock cladding has resulted in significant corrosion and deterioration most particularly to the imitation rock cladding layer but also to the supporting concrete frame. In some areas light was visible through the cladding layer indicating areas of water ingress.
The report concluded that the extent of spalling damage observed to the structural framing of the mountain has not yet severely compromised the structural integrity. However, if the damage is left untreated and allowed to continue, it will eventually result in localised beam/column failures, which could compromise the stability of the structure and necessitate extensive remedial works or demolition. The report identifies action to repair the reinforced concrete frame. In relation to the ferro-concrete cladding the report states that it is generally in very poor condition, and localised failures could occur at any time where, dependent on their extent, could result in the injury/death of animals on the mountain. The report recommends that internal repair of the cladding be undertaken, using temporary propping of cladding panels between supporting columns to allow for drummy material and heavily corroded reinforcement to be cut back and removed, prior to installing new reinforcement and reinstating the original surface profile by spraying with shotcrete.
This makes it sound like Tahr were already on their way out prior to the reintroduction of Lions to the site. They had to be moved nevertheless however in order to accommodate the Pride, so it's not as alarming a move as it could have potentially been, had the structural engineers not caught wind of it.